Constitution Part 4 - Contract procedure rules

Part B - Select lists of contractors

2. Compilation of a Select List of Contractors

  • i) This rule applies where a decision has been made that a list shall be kept of persons to be invited to submit quotations for contracts for the supply of goods, materials or services of specified categories, values or amounts, or for the execution of specified categories of work.
  • ii) The list shall include, where possible, a minimum of four persons, wherever practicable two of which should be local to Hartlepool, and shall;
    • be approved by the Chief Officer;
    • contain the names of all persons included in it subject to their approval by the Chief Officer/Head of Department, the appropriate technical officer (being satisfied that they have the capacity to undertake the contracts envisaged), the Health, Safety and Wellbeing Manager or Chief Executive’s nominee (being satisfied that they have adequate Health and Safety arrangements) and the Director of Finance, IT and Digital (being satisfied that they are financially sound); and
    • indicate whether a person whose name is included in it is approved for contracts for all or only some of the specified values or amounts of categories. 
  • iii) At least four weeks before the list is first compiled, notices inviting applications for inclusion in it shall be published:
    • a. in one or more local newspapers circulating in the district, and/or
    • b. on the procurement pages of the Council’s website, and/or
    • c. in one or more newspapers or journals circulating among such persons as undertake contracts of the specified values or amounts or categories.
  • iv) The list may be amended by the appropriate Chief Officer as required from time to time and shall be reviewed as follows:
    • Review to be carried out at intervals not exceeding 4 years, where an update of the list is carried out and notices inviting applications for inclusion in the list shall be published in the manner provided by paragraph (iii) of this section.
    • Update to be carried out at intervals not exceeding 2 years, where each person whose name appears in the list shall be asked whether s/he wishes his/her name to remain therein.

Any such amendment or update shall be approved by the Chief Officer.

3. Adoption / Development of Corporate or Collaborative framework agreements

  • i) This rule applies where a decision has been made to adopt or develop a framework agreement corporately and where the agreement is to be used exclusively with no ‘off-contract’ purchases being made.
  • ii) When developing / adopting framework agreements for corporate use, the agreement must include a number of suppliers appropriate to the nature and subject of the framework agreement.
  • iii) The maximum duration of any such framework agreement is 4 years. This limit refers to the duration of the framework agreement and not any contracts implemented via the framework agreement. The duration of Framework Agreements may not be extended beyond the 4 year limit.
  • iv) Procurement processes and public notice provisions for developing framework agreements are the same as those detailed in Part C Procurement Procedures.
  • v) Any exemptions relating to the use of alternative procurement routes to approved Corporate framework agreements (for goods / works / services covered by approved Corporate framework agreements) are to be requested from the Council’s Corporate Lead for Procurement and will be reported to the Finance and Corporate Affairs Committee on a quarterly basis.