Technical annex 2026/27 - Local highways maintenance transparency report

2.0 Highway maintenance activity (surface treatments and repairs)

2.1 Road resurfacing and surface treatments

Financial year

Road receiving preventative road surface treatments (length, km)

Road receiving planned structural maintenance (length, km)

Area receiving planned repair / patching programmes

Area receiving reactive repair / patching (permanent methods)

Area receiving reactive repairs/ patching (temporary methods)

2025-26

0 km

6.1 km

 0 m2

799 m2

200 m2

2026-27 projected

1 km

7.5 km

0 m2

n/a

n/a

2.1.1 additional information on surface treatments and repairs

Does table B2.1 reflect all your carriageway-related road surface treatments & repair activities (for example, including pothole repairs)? If no, please add further information on any other types of treatments (planned to be) delivered and their extent in the table below.

No

2.1.2 – Further information and context

Hartlepool Borough Council have planned in trial surveys to be undertaken on a stretch of dual carriageway running through the town centre (A689) with the idea of implementing preventative maintenance on the concrete base blocks used on this road in an effort to prolong their life. The Council are also actively investigating suitable roads to include in a surface dressing programme for 2026/27 – road surveys from 25/26 and 26/27 will be used to support this investigation.